In a Kanban system applied to IT service management, what is the primary purpose of setting Work-in-Progress (WIP) limits?
-
A
To ensure team members always have maximum tasks assigned
-
B
To reduce context switching and improve flow efficiency
-
C
To eliminate the need for sprint planning ceremonies
-
D
To increase the total throughput by adding more parallel work