A project manager calculates an Estimate at Completion (EAC) using the formula EAC = BAC / CPI. Under what assumption is this formula most appropriate?
-
A
Future work will be performed at the planned rate
-
B
Future cost performance will mirror the current CPI
-
C
The remaining work has no cost risk
-
D
The schedule variance will be recovered by project end