MEM Principles of Project Management 4 — Questions and Answers
Question 1: A project manager calculates an Estimate at Completion (EAC) using the formula EAC = BAC / CPI. Under what assumption is this formula most appropriate?
- Future work will be performed at the planned rate
- Future cost performance will mirror the current CPI (Correct answer)
- The remaining work has no cost risk
- The schedule variance will be recovered by project end
Correct answer: Future cost performance will mirror the current CPI
EAC = BAC / CPI assumes current spending efficiency will continue throughout the remainder of the project.
Question 2: Which document formally authorizes a project and names the project manager, granting authority to apply organizational resources?
- Project management plan
- Project charter (Correct answer)
- Business case
- Scope statement
Correct answer: Project charter
The project charter is issued by a sponsor and officially authorizes the project and the project manager's role.
Question 3: A project manager uses a probability-impact matrix. Which risk quadrant demands the MOST immediate attention?
- Low probability, high impact
- Low probability, low impact
- High probability, low impact
- High probability, high impact (Correct answer)
Correct answer: High probability, high impact
Risks with both high probability and high impact represent the greatest threat and require priority response planning.
Question 4: What is 'scope creep' in project management?
- Gradual reduction in project scope due to budget cuts
- Uncontrolled expansion of project scope without proper approval (Correct answer)
- Planned incremental additions documented in change orders
- Reassignment of work packages to different team members
Correct answer: Uncontrolled expansion of project scope without proper approval
Scope creep occurs when new features or work are added to a project without following the change control process.
Question 5: In earned value management, what does a negative Schedule Variance (SV) indicate?
- The project is over budget
- The project is behind schedule (Correct answer)
- The project is ahead of schedule
- The project has exceeded its scope baseline
Correct answer: The project is behind schedule
SV = EV − PV; a negative result means less work has been completed (earned) than was planned at that point in time.
Question 6: Which stakeholder engagement level is represented when a stakeholder actively participates and supports the project?
- Unaware
- Resistant
- Supportive
- Champion (Correct answer)
Correct answer: Champion
A champion actively promotes the project and uses their influence to ensure its success beyond mere support.
Question 7: A work breakdown structure (WBS) is considered complete when it reaches the level of:
- Project phases
- Work packages that can be estimated, scheduled, and assigned (Correct answer)
- Individual task steps for each team member
- Deliverables approved by the project sponsor
Correct answer: Work packages that can be estimated, scheduled, and assigned
Work packages are the lowest level of the WBS and represent discrete scope that can be reliably estimated and controlled.
A project manager calculates an Estimate at Completion (EAC) using the formula EAC = BAC / CPI.
Under what assumption is this formula most appropriate?