General Contractor License Business and Finance Management 4 β Questions and Answers
Question 1: A contractor wants to determine if a project is profitable mid-job. Which document provides the best real-time comparison of budgeted vs. actual costs?
- General ledger
- Job cost report (Correct answer)
- Accounts payable aging report
- Balance sheet
Correct answer: Job cost report
A job cost report compares estimated costs to actual costs incurred, allowing mid-project profitability analysis by cost category.
Question 2: Under the completed-contract accounting method, revenue and expenses are recognized:
- Monthly based on invoices submitted
- When the project reaches substantial completion (Correct answer)
- As materials are delivered to the job site
- When the subcontractors are paid
Correct answer: When the project reaches substantial completion
The completed-contract method defers all revenue and expense recognition until the project is substantially complete.
Question 3: An owner withholds 10% of each progress payment until project completion. This withheld amount is called:
- Liquidated damages
- Retainage (Correct answer)
- Mobilization fee
- Contingency reserve
Correct answer: Retainage
Retainage is a percentage of earned payment withheld by the owner as security to ensure the contractor completes the work satisfactorily.
Question 4: Which of the following is considered a direct cost on a construction project?
- Office rent
- Field supervisor wages on the job site (Correct answer)
- Company vehicle insurance
- Accounting software subscription
Correct answer: Field supervisor wages on the job site
Direct costs are directly attributable to a specific project, including on-site labor, materials, and equipment used for that job.
Question 5: A contractor's net profit margin is 5% on a $2,000,000 project. What is the net profit?
- $10,000
- $50,000
- $100,000 (Correct answer)
- $200,000
Correct answer: $100,000
Net profit = Revenue Γ Profit margin: $2,000,000 Γ 5% = $100,000.
Question 6: Which type of estimate is typically most accurate and used as the basis for a formal bid?
- Ballpark estimate
- Conceptual estimate
- Detailed quantity takeoff estimate (Correct answer)
- Square footage estimate
Correct answer: Detailed quantity takeoff estimate
A detailed quantity takeoff estimate quantifies every material and labor unit required, providing the highest level of accuracy for bidding.
Question 7: A contractor who fails to carry required workers' compensation insurance may face which consequence?
- Reduced bonding capacity only
- License suspension, fines, and personal liability for worker injuries (Correct answer)
- Mandatory project shutdown for 30 days
- Loss of general liability coverage only
Correct answer: License suspension, fines, and personal liability for worker injuries
Operating without required workers' compensation exposes contractors to license revocation, significant fines, and direct liability for injured workers' costs.
A contractor wants to determine if a project is profitable mid-job.
Which document provides the best real-time comparison of budgeted vs. actual costs?