General Contractor License Business and Finance Management — Questions and Answers
Question 1: A contractor's overhead rate is calculated by dividing total overhead costs by which figure?
- Gross revenue
- Direct labor costs (Correct answer)
- Net profit
- Total material costs
Correct answer: Direct labor costs
Overhead rate is calculated by dividing total overhead costs by direct labor costs to allocate indirect expenses to projects.
Question 2: Which financial statement shows a contractor's assets, liabilities, and equity at a specific point in time?
- Income statement
- Cash flow statement
- Balance sheet (Correct answer)
- Work-in-progress schedule
Correct answer: Balance sheet
The balance sheet is a snapshot of financial position at a given date, showing what the company owns versus what it owes.
Question 3: A subcontractor fails to complete work and causes a project delay. Under a typical subcontract agreement, the general contractor may:
- Withhold all future payments permanently
- Back-charge the subcontractor for resulting costs (Correct answer)
- Terminate all subcontracts on the project
- File a mechanics lien against the subcontractor
Correct answer: Back-charge the subcontractor for resulting costs
Back-charges allow the GC to deduct costs incurred due to a subcontractor's default from amounts owed to that subcontractor.
Question 4: What does the term 'accounts receivable turnover' measure in a contracting business?
- How quickly the company pays its suppliers
- How efficiently the company collects money owed to it (Correct answer)
- The ratio of revenue to total assets
- The average cost per project completed
Correct answer: How efficiently the company collects money owed to it
Accounts receivable turnover measures how many times receivables are collected over a period, indicating billing and collection efficiency.
Question 5: A contractor purchases a $120,000 piece of equipment with a 5-year useful life and $0 salvage value. Using straight-line depreciation, the annual depreciation expense is:
- $12,000
- $24,000 (Correct answer)
- $30,000
- $60,000
Correct answer: $24,000
Straight-line depreciation divides cost by useful life: $120,000 ÷ 5 = $24,000 per year.
Question 6: Which type of bond guarantees that a contractor will pay subcontractors and material suppliers on a project?
- Bid bond
- Performance bond
- Payment bond (Correct answer)
- License bond
Correct answer: Payment bond
A payment bond protects subcontractors and suppliers by guaranteeing they will be paid even if the general contractor defaults.
Question 7: When preparing a job cost report, 'cost to complete' refers to:
- Total costs spent on the project to date
- Estimated remaining costs needed to finish the project (Correct answer)
- The original contract price minus profit
- Overhead costs allocated to the job
Correct answer: Estimated remaining costs needed to finish the project
Cost to complete is the projected amount still needed to finish the project, used to forecast final job profitability.
Question 8: A contractor's current ratio is calculated as current assets divided by current liabilities. A ratio below 1.0 generally indicates:
- Strong short-term financial health
- Insufficient liquidity to cover short-term obligations (Correct answer)
- High profitability
- Excessive overhead costs
Correct answer: Insufficient liquidity to cover short-term obligations
A current ratio below 1.0 means the company has more short-term debts than short-term assets, signaling potential cash flow problems.
Question 9: Under the percentage-of-completion accounting method, revenue is recognized:
- Only when the project reaches final completion
- Based on the proportion of work completed to date (Correct answer)
- When the client makes each scheduled payment
- At the start of the contract
Correct answer: Based on the proportion of work completed to date
Percentage-of-completion recognizes revenue proportionally as work progresses, matching revenue with costs incurred.
Question 10: A general contractor wants to protect against losses from employee theft. Which type of insurance is most appropriate?
- General liability insurance
- Workers' compensation insurance
- Commercial crime or fidelity bond insurance (Correct answer)
- Builder's risk insurance
Correct answer: Commercial crime or fidelity bond insurance
Commercial crime insurance or fidelity bonds cover losses resulting from employee dishonesty, including theft of money or property.
Question 11: What is the primary purpose of a 'schedule of values' in construction contracts?
- To list the project's timeline milestones
- To break down the contract sum for progress billing purposes (Correct answer)
- To document material quantities required
- To rank subcontractors by cost
Correct answer: To break down the contract sum for progress billing purposes
A schedule of values allocates the contract sum across work items, forming the basis for monthly progress payment applications.
Question 12: If a contractor's bid is $500,000 and the owner requests a 10% reduction, what technique should the contractor use to identify where savings are possible?
- Increase markup to compensate
- Perform value engineering to reduce scope or find alternatives (Correct answer)
- Reduce the contingency to zero
- Eliminate all subcontractor fees
Correct answer: Perform value engineering to reduce scope or find alternatives
Value engineering systematically analyzes project components to find cost-effective alternatives that maintain required function and quality.
Question 13: A contractor collects a deposit before starting work. On the balance sheet, this unearned revenue is classified as:
- An asset
- Owner's equity
- A liability (Correct answer)
- Operating income
Correct answer: A liability
Unearned revenue (deposits collected before work is performed) is a liability because the contractor owes the service to the client.
Question 14: Which document formally establishes the scope of work, payment terms, and legal obligations between a general contractor and owner?
- Certificate of insurance
- Construction contract (Correct answer)
- Notice to proceed
- Lien waiver
Correct answer: Construction contract
The construction contract is the legally binding agreement defining the rights, responsibilities, and obligations of both parties.
Question 15: A contractor wants to determine if a project is profitable mid-job. Which document provides the best real-time comparison of budgeted vs. actual costs?
- General ledger
- Job cost report (Correct answer)
- Accounts payable aging report
- Balance sheet
Correct answer: Job cost report
A job cost report compares estimated costs to actual costs incurred, allowing mid-project profitability analysis by cost category.
Question 16: Under the completed-contract accounting method, revenue and expenses are recognized:
- Monthly based on invoices submitted
- When the project reaches substantial completion (Correct answer)
- As materials are delivered to the job site
- When the subcontractors are paid
Correct answer: When the project reaches substantial completion
The completed-contract method defers all revenue and expense recognition until the project is substantially complete.
Question 17: An owner withholds 10% of each progress payment until project completion. This withheld amount is called:
- Liquidated damages
- Retainage (Correct answer)
- Mobilization fee
- Contingency reserve
Correct answer: Retainage
Retainage is a percentage of earned payment withheld by the owner as security to ensure the contractor completes the work satisfactorily.
Question 18: Which of the following is considered a direct cost on a construction project?
- Office rent
- Field supervisor wages on the job site (Correct answer)
- Company vehicle insurance
- Accounting software subscription
Correct answer: Field supervisor wages on the job site
Direct costs are directly attributable to a specific project, including on-site labor, materials, and equipment used for that job.
Question 19: A contractor's net profit margin is 5% on a $2,000,000 project. What is the net profit?
- $10,000
- $50,000
- $100,000 (Correct answer)
- $200,000
Correct answer: $100,000
Net profit = Revenue × Profit margin: $2,000,000 × 5% = $100,000.
Question 20: Which type of estimate is typically most accurate and used as the basis for a formal bid?
- Ballpark estimate
- Conceptual estimate
- Detailed quantity takeoff estimate (Correct answer)
- Square footage estimate
Correct answer: Detailed quantity takeoff estimate
A detailed quantity takeoff estimate quantifies every material and labor unit required, providing the highest level of accuracy for bidding.
Question 21: A contractor who fails to carry required workers' compensation insurance may face which consequence?
- Reduced bonding capacity only
- License suspension, fines, and personal liability for worker injuries (Correct answer)
- Mandatory project shutdown for 30 days
- Loss of general liability coverage only
Correct answer: License suspension, fines, and personal liability for worker injuries
Operating without required workers' compensation exposes contractors to license revocation, significant fines, and direct liability for injured workers' costs.