Business and Finance Management Flashcards
21 cards from real General Contractor License practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 20 Business and Finance Management flashcards as text
A contractor's overhead rate is calculated by dividing total overhead costs by which figure?
Answer: Direct labor costs
Overhead rate is calculated by dividing total overhead costs by direct labor costs to allocate indirect expenses to projects.
Which financial statement shows a contractor's assets, liabilities, and equity at a specific point in time?
Answer: Balance sheet
The balance sheet is a snapshot of financial position at a given date, showing what the company owns versus what it owes.
A subcontractor fails to complete work and causes a project delay. Under a typical subcontract agreement, the general contractor may:
Answer: Back-charge the subcontractor for resulting costs
Back-charges allow the GC to deduct costs incurred due to a subcontractor's default from amounts owed to that subcontractor.
What does the term 'accounts receivable turnover' measure in a contracting business?
Answer: How efficiently the company collects money owed to it
Accounts receivable turnover measures how many times receivables are collected over a period, indicating billing and collection efficiency.
A contractor purchases a $120,000 piece of equipment with a 5-year useful life and $0 salvage value. Using straight-line depreciation, the annual depreciation expense is:
Answer: $24,000
Straight-line depreciation divides cost by useful life: $120,000 ÷ 5 = $24,000 per year.
Which type of bond guarantees that a contractor will pay subcontractors and material suppliers on a project?
Answer: Payment bond
A payment bond protects subcontractors and suppliers by guaranteeing they will be paid even if the general contractor defaults.
When preparing a job cost report, 'cost to complete' refers to:
Answer: Estimated remaining costs needed to finish the project
Cost to complete is the projected amount still needed to finish the project, used to forecast final job profitability.
A contractor's current ratio is calculated as current assets divided by current liabilities. A ratio below 1.0 generally indicates:
Answer: Insufficient liquidity to cover short-term obligations
A current ratio below 1.0 means the company has more short-term debts than short-term assets, signaling potential cash flow problems.
Under the percentage-of-completion accounting method, revenue is recognized:
Answer: Based on the proportion of work completed to date
Percentage-of-completion recognizes revenue proportionally as work progresses, matching revenue with costs incurred.
A general contractor wants to protect against losses from employee theft. Which type of insurance is most appropriate?
Answer: Commercial crime or fidelity bond insurance
Commercial crime insurance or fidelity bonds cover losses resulting from employee dishonesty, including theft of money or property.
What is the primary purpose of a 'schedule of values' in construction contracts?
Answer: To break down the contract sum for progress billing purposes
A schedule of values allocates the contract sum across work items, forming the basis for monthly progress payment applications.
If a contractor's bid is $500,000 and the owner requests a 10% reduction, what technique should the contractor use to identify where savings are possible?
Answer: Perform value engineering to reduce scope or find alternatives
Value engineering systematically analyzes project components to find cost-effective alternatives that maintain required function and quality.
A contractor collects a deposit before starting work. On the balance sheet, this unearned revenue is classified as:
Answer: A liability
Unearned revenue (deposits collected before work is performed) is a liability because the contractor owes the service to the client.
Which document formally establishes the scope of work, payment terms, and legal obligations between a general contractor and owner?
Answer: Construction contract
The construction contract is the legally binding agreement defining the rights, responsibilities, and obligations of both parties.
A contractor wants to determine if a project is profitable mid-job. Which document provides the best real-time comparison of budgeted vs. actual costs?
Answer: Job cost report
A job cost report compares estimated costs to actual costs incurred, allowing mid-project profitability analysis by cost category.
Under the completed-contract accounting method, revenue and expenses are recognized:
Answer: When the project reaches substantial completion
The completed-contract method defers all revenue and expense recognition until the project is substantially complete.
An owner withholds 10% of each progress payment until project completion. This withheld amount is called:
Answer: Retainage
Retainage is a percentage of earned payment withheld by the owner as security to ensure the contractor completes the work satisfactorily.
Which of the following is considered a direct cost on a construction project?
Answer: Field supervisor wages on the job site
Direct costs are directly attributable to a specific project, including on-site labor, materials, and equipment used for that job.
A contractor's net profit margin is 5% on a $2,000,000 project. What is the net profit?
Answer: $100,000
Net profit = Revenue × Profit margin: $2,000,000 × 5% = $100,000.
Which type of estimate is typically most accurate and used as the basis for a formal bid?
Answer: Detailed quantity takeoff estimate
A detailed quantity takeoff estimate quantifies every material and labor unit required, providing the highest level of accuracy for bidding.
Written and edited by Nathan Beja, founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- cslb.ca.gov — Fees, renewal · verified Oct 2026
- web.cslb.ca.gov — Test delivery, exam format, retake policy, score release, score validity · verified Oct 2026
- test-takers.psiexams.com — Exam format, passing score, retake policy, score release, time limit, score validity · verified Oct 2026
- psiexams.com — Eligibility · verified Oct 2026
- www2.myfloridalicense.com — Registration deadline, exam format, passing score, test delivery · verified Oct 2026