← All General Contractor License Flashcard Decks

Business and Finance Management Flashcards

7 cards from real General Contractor License practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Business and Finance Management flashcards as text
  1. A contractor's overhead rate is calculated by dividing total overhead costs by which figure?

    Answer: Direct labor costs

    Overhead rate is calculated by dividing total overhead costs by direct labor costs to allocate indirect expenses to projects.

  2. Which financial statement shows a contractor's assets, liabilities, and equity at a specific point in time?

    Answer: Balance sheet

    The balance sheet is a snapshot of financial position at a given date, showing what the company owns versus what it owes.

  3. A subcontractor fails to complete work and causes a project delay. Under a typical subcontract agreement, the general contractor may:

    Answer: Back-charge the subcontractor for resulting costs

    Back-charges allow the GC to deduct costs incurred due to a subcontractor's default from amounts owed to that subcontractor.

  4. What does the term 'accounts receivable turnover' measure in a contracting business?

    Answer: How efficiently the company collects money owed to it

    Accounts receivable turnover measures how many times receivables are collected over a period, indicating billing and collection efficiency.

  5. A contractor purchases a $120,000 piece of equipment with a 5-year useful life and $0 salvage value. Using straight-line depreciation, the annual depreciation expense is:

    Answer: $24,000

    Straight-line depreciation divides cost by useful life: $120,000 ÷ 5 = $24,000 per year.

  6. Which type of bond guarantees that a contractor will pay subcontractors and material suppliers on a project?

    Answer: Payment bond

    A payment bond protects subcontractors and suppliers by guaranteeing they will be paid even if the general contractor defaults.

  7. When preparing a job cost report, 'cost to complete' refers to:

    Answer: Estimated remaining costs needed to finish the project

    Cost to complete is the projected amount still needed to finish the project, used to forecast final job profitability.