A contractor uses an AWS D1.1 prequalified WPS for a structural steel project. Which statement about prequalified WPSs is correct?
-
A
They require a PQR to support them before use
-
B
They do not require testing if all prequalified conditions are met
-
C
They must be qualified by a third-party testing laboratory
-
D
They are valid only for fillet welds, not groove welds