A CWI is reviewing a WPS and notices the interpass temperature is not listed. What should the inspector do?
-
A
Accept the WPS since interpass temperature is not required
-
B
Reject the WPS because interpass temperature is always mandatory
-
C
Verify whether the applicable code requires interpass temperature on the WPS
-
D
Request the welder determine the interpass temperature during welding