A stakeholder requests adding a new feature after the scope baseline has been approved. What should the project coordinator do FIRST?
-
A
Add the feature to avoid stakeholder dissatisfaction
-
B
Reject the request outright to protect the baseline
-
C
Submit a formal change request and assess the impact
-
D
Reassign team members to accommodate the new feature