In Kotter's model, what is the purpose of 'creating short-term wins' (Step 6)?
-
A
To finalize the change project and close it out
-
B
To demonstrate early progress, build momentum, and silence critics of the change
-
C
To reward executives for approving the budget
-
D
To document lessons learned for future projects