A project's Estimate at Completion (EAC) is calculated as BAC / CPI. This formula assumes:
-
A
Future work will be performed at the budgeted rate
-
B
The current cost performance will continue for the remainder of the project
-
C
The project scope will be reduced to meet the budget
-
D
All remaining work will be completed at zero cost