CCM - Certified Construction Manager CCM Cost and Time Management Questions and Answers
A construction project's performance is being tracked using Earned Value Management (EVM). At the end of a reporting period, the following data is available: Budget at Completion (BAC) = $1,500,000, Planned Value (PV) = $700,000, Earned Value (EV) = $650,000, and Actual Cost (AC) = $680,000. Based on this data, what is the status of the project?