A Scrum Master notices the Daily Scrum regularly runs 35 minutes. What is the most appropriate action?
-
A
Coach the Developers to keep it within the 15-minute timebox
-
B
Cancel the Daily Scrum for a week
-
C
Take over and run the meeting personally
-
D
Report the team to management