Project Management Agile and Scrum Ceremonies — Questions and Answers
Question 1: A Scrum Master notices that Sprint Reviews consistently run over their timebox. What is the recommended timebox for a Sprint Review in a one-month Sprint?
- 2 hours
- 4 hours (Correct answer)
- 8 hours
- 1 hour
Correct answer: 4 hours
The Scrum Guide specifies a maximum of 4 hours for a Sprint Review in a one-month Sprint, with shorter Sprints having proportionally shorter reviews.
Question 2: Which Scrum ceremony is primarily focused on creating a shared understanding of the work needed to achieve the Sprint Goal?
- Daily Scrum
- Sprint Retrospective
- Sprint Planning (Correct answer)
- Sprint Review
Correct answer: Sprint Planning
Sprint Planning creates shared understanding by defining the Sprint Goal and selecting and decomposing Product Backlog items into actionable Sprint Backlog tasks.
Question 3: During a Sprint Retrospective, a team uses the 'Start, Stop, Continue' format. Which category would 'pair programming sessions' most likely fall into if the team wants to adopt it going forward?
- Stop
- Continue
- Start (Correct answer)
- Inspect
Correct answer: Start
Practices the team wants to adopt that they haven't tried yet belong in the 'Start' category of the Start, Stop, Continue retrospective format.
Question 4: A product owner is unavailable for Sprint Planning. What should the Scrum Master do?
- Cancel the Sprint Planning and reschedule (Correct answer)
- Let the Development Team plan without the Product Owner
- Postpone the Sprint until the Product Owner is available
- Have the Scrum Master represent the Product Owner
Correct answer: Cancel the Sprint Planning and reschedule
Sprint Planning requires the Product Owner to clarify backlog items and accept the Sprint Goal, so it should be rescheduled rather than held without them.
Question 5: What is the primary output of Sprint Planning?
- Updated Product Backlog
- Sprint Backlog and Sprint Goal (Correct answer)
- Release plan for the increment
- Burndown chart
Correct answer: Sprint Backlog and Sprint Goal
Sprint Planning produces the Sprint Backlog (selected items and a plan for delivering them) and a Sprint Goal that provides cohesive direction.
Question 6: In Kanban, which meeting is the closest equivalent to the Scrum Daily Standup?
- Flow review
- Replenishment meeting
- Daily standup or queue replenishment (Correct answer)
- Retrospective
Correct answer: Daily standup or queue replenishment
Kanban also uses a daily standup (often called a daily Kanban meeting) to review flow and blockers, serving a similar synchronization purpose as the Scrum Daily Scrum.
Question 7: A team member raises a technical design concern during the Daily Scrum. What is the correct Scrum approach?
- Pause the Daily Scrum to resolve the issue
- Ignore it until the Sprint Review
- Note it and address it in a separate follow-up meeting after the Daily Scrum (Correct answer)
- Escalate it to the Product Owner immediately
Correct answer: Note it and address it in a separate follow-up meeting after the Daily Scrum
The Daily Scrum is timeboxed to 15 minutes for synchronization; detailed discussions should happen in follow-up meetings with relevant team members.
Question 8: What distinguishes a Sprint Retrospective from a Sprint Review in terms of audience?
- The Retrospective includes stakeholders; the Review does not
- The Review includes stakeholders; the Retrospective is for the Scrum Team only (Correct answer)
- Both include all stakeholders
- Neither includes the Product Owner
Correct answer: The Review includes stakeholders; the Retrospective is for the Scrum Team only
The Sprint Review is an open inspection where stakeholders are invited, while the Sprint Retrospective is an internal Scrum Team ceremony focused on continuous improvement.
Question 9: Which statement best describes the relationship between the Sprint Goal and Sprint Planning?
- The Sprint Goal is created after Sprint Planning ends
- The Sprint Goal is brought by the Product Owner and refined during Sprint Planning (Correct answer)
- The Sprint Goal is set by the Scrum Master based on velocity
- The Sprint Goal is optional and set only for long Sprints
Correct answer: The Sprint Goal is brought by the Product Owner and refined during Sprint Planning
The Product Owner proposes a Sprint Goal before planning, and the Scrum Team crafts the final Sprint Goal collaboratively during Sprint Planning.
Question 10: A Scrum Team completes its Increment but realizes the Sprint Goal was not fully met. What should happen at the Sprint Review?
- Cancel the Sprint Review since the goal was missed
- Skip the demo and move directly to the Retrospective
- Present what was done, discuss the gap, and adapt the Product Backlog accordingly (Correct answer)
- Extend the Sprint to meet the original goal
Correct answer: Present what was done, discuss the gap, and adapt the Product Backlog accordingly
The Sprint Review is an inspect-and-adapt event where the team presents the Increment, discusses what happened, and updates the Product Backlog based on new understanding.
Question 11: What is the maximum timebox for a Daily Scrum?
- 30 minutes
- 15 minutes (Correct answer)
- 10 minutes
- 1 hour
Correct answer: 15 minutes
The Daily Scrum is timeboxed to 15 minutes regardless of team size, promoting discipline and efficiency in daily synchronization.
Question 12: During Backlog Refinement, who is responsible for clarifying the details of Product Backlog items?
- Only the Product Owner
- Only the Development Team
- The Scrum Master and Stakeholders
- The Product Owner and Developers collaboratively (Correct answer)
Correct answer: The Product Owner and Developers collaboratively
Backlog Refinement is a collaborative activity where the Product Owner and Developers add detail, estimates, and order to Product Backlog items.
Question 13: Which Agile principle directly supports the purpose of holding frequent Sprint Reviews?
- Working software is the primary measure of progress (Correct answer)
- The best architectures emerge from self-organizing teams
- Continuous attention to technical excellence
- Business people and developers must work together daily
Correct answer: Working software is the primary measure of progress
The Agile principle that working software is the primary measure of progress directly supports Sprint Reviews, where teams demonstrate a potentially shippable Increment.
Question 14: A newly formed Scrum Team asks how long each Sprint should be. What guidance does the Scrum Guide provide?
- Exactly 2 weeks
- Between 1 and 4 weeks, chosen by the team (Correct answer)
- Between 2 and 6 weeks, chosen by the Product Owner
- 1 week only for new teams
Correct answer: Between 1 and 4 weeks, chosen by the team
The Scrum Guide recommends Sprints be one month or less, with the team choosing the specific length to maintain a consistent cadence.
Question 15: A Product Owner wants to cancel a Sprint. Under what condition does the Scrum Guide permit Sprint cancellation?
- When the team's velocity drops significantly
- When the Sprint Goal becomes obsolete (Correct answer)
- When more than half the Sprint Backlog is incomplete
- When a key developer leaves the team
Correct answer: When the Sprint Goal becomes obsolete
Only the Product Owner can cancel a Sprint, and only when the Sprint Goal becomes obsolete due to changed priorities, business conditions, or company direction.
Question 16: In SAFe (Scaled Agile Framework), what ceremony replaces the individual Sprint Review at the program level?
- Program Increment Planning
- System Demo (Correct answer)
- Inspect and Adapt Workshop
- Release Train Engineer sync
Correct answer: System Demo
The System Demo in SAFe is the program-level equivalent of the Sprint Review, where all Agile Release Train teams demonstrate integrated working software.
Question 17: What three questions traditionally structure the Daily Scrum?
- What did I plan, what did I do, why is there a gap?
- What did I do yesterday, what will I do today, are there any impediments? (Correct answer)
- What is my status, what is my priority, what help do I need?
- What is done, what is in progress, what is blocked?
Correct answer: What did I do yesterday, what will I do today, are there any impediments?
The traditional Daily Scrum uses three questions: what was accomplished yesterday, what will be done today, and what impediments exist — though the Scrum Guide now allows any structure that meets the goal.
Question 18: A Scrum Master observes that the team's Sprint Retrospectives produce action items that are never completed. What is the best response?
- Stop holding Retrospectives until team culture improves
- Add retrospective action items to the Sprint Backlog (Correct answer)
- Report the team to management
- Replace the retrospective with a written survey
Correct answer: Add retrospective action items to the Sprint Backlog
Adding retrospective improvement actions to the Sprint Backlog makes them visible, tracked, and prioritized alongside other work, increasing the chance of completion.
Question 19: Which Scrum event provides the opportunity for the Scrum Team to inspect the Definition of Done and improve it?
- Daily Scrum
- Sprint Review
- Sprint Planning
- Sprint Retrospective (Correct answer)
Correct answer: Sprint Retrospective
The Sprint Retrospective is where the team inspects their processes, tools, and quality standards — including reviewing and strengthening the Definition of Done.
Question 20: An Agile coach recommends 'timeboxing' all meetings. What is the primary benefit of timeboxing Scrum ceremonies?
- It ensures all agenda items are covered
- It creates urgency and prevents waste from open-ended discussions (Correct answer)
- It allows more meetings to be scheduled per day
- It replaces the need for a facilitator
Correct answer: It creates urgency and prevents waste from open-ended discussions
Timeboxing creates a sense of urgency that focuses discussion, prevents rambling conversations, and respects team members' time — a core Scrum discipline.
Question 21: During Sprint Planning, the Development Team determines they cannot complete all items the Product Owner wants. What should happen?
- The Product Owner overrides the team and adds the items anyway
- The team negotiates scope with the Product Owner to fit the Sprint capacity (Correct answer)
- The Scrum Master decides what gets included
- The Sprint is extended to accommodate all items
Correct answer: The team negotiates scope with the Product Owner to fit the Sprint capacity
The Development Team owns the commitment to the Sprint Backlog and negotiates scope with the Product Owner to ensure the Sprint Goal is achievable within capacity.
A Scrum Master notices that Sprint Reviews consistently run over their timebox.
What is the recommended timebox for a Sprint Review in a one-month Sprint?
What Practice Test Geeks adds beyond an AI chat for Project Management
An AI chatbot can quiz you, but it can't reproduce the exam conditions or keep your record. Here you get:
- A timed, full-length Project Management mock exam — 180 questions in 230 minutes with a 61% pass mark, modeled on the official exam's question count and time limit, followed by a score report broken down by exam domain.
- A fixed Project Management question bank: the same test every attempt, so your score is comparable from one try to the next instead of changing with every regenerated quiz.
- Progress saved on your device: completed tests, scores and missed questions stay in My Progress, so you can retake only what you got wrong.
- A printable Project Management cheat sheet you can print or save as a PDF.
- Project Management flashcards built from the same question bank.
These practice questions were written with AI tools. They are not real exam questions. We have not yet matched this exam's facts to an official source, so confirm fees, dates and rules with the exam body. Not reviewed by a subject-matter expert. Editorial policy