The Scrum Master is asked to prepare a project plan with fixed milestones for senior leadership. How should the Scrum Master respond?
-
A
Create the plan since leadership's needs are paramount
-
B
Decline entirely as planning is not part of the Scrum Master role
-
C
Help leadership understand empiricism and how Scrum creates transparency through Sprints and forecasts
-
D
Delegate the planning task to the Product Owner