During Sprint Planning, the Developers realize they cannot complete all the work the Product Owner wants. What should happen?
-
A
The Scrum Master decides the final Sprint scope
-
B
The Developers negotiate with the Product Owner to select a feasible amount of work
-
C
The Product Owner must reduce the Sprint length to fit the work
-
D
Developers must commit to all the work requested by the Product Owner