Why does Scrum avoid providing detailed, prescriptive processes for complex work?
-
A
Because detailed processes are too expensive to document
-
B
Because complex work is unpredictable and outcomes cannot be fully known in advance
-
C
Because Scrum teams are self-managing and dislike rules
-
D
Because Agile coaches prefer flexibility over structure