A Scrum Master is asked by a manager to evaluate individual developer performance based on Sprint velocity. What is the BEST response?
-
A
Agree and produce individual velocity metrics for each developer
-
B
Explain that velocity is a team measure and using it for individual evaluation undermines collaboration
-
C
Delegate the task to the Product Owner who manages the backlog
-
D
Provide the metrics but add a disclaimer that they may not be accurate