A Scrum Master notices the Development Team consistently avoids raising impediments during the Daily Scrum. What is the BEST first action?
-
A
Mandate that each Developer must report at least one impediment per day
-
B
Create a private channel so developers can report impediments anonymously
-
C
Facilitate a retrospective focused on psychological safety and why impediments go unreported
-
D
Escalate the issue to senior management to enforce transparency