Which statement about the Sprint is correct from a Scrum facilitation perspective?
-
A
Sprints can be extended if the Development Team needs more time to complete all Sprint Backlog items
-
B
The Sprint is a container for all other Scrum events and should not be extended or shortened mid-Sprint
-
C
The Scrum Master can pause the Sprint if the team encounters a major impediment
-
D
The Product Owner can add work to the Sprint Backlog at any time without consulting the team