During a Sprint Review, the Product Owner announces a major market shift that invalidates half the Sprint's work. What should the Scrum Master facilitate next?
-
A
End the Sprint Review early and start a new Sprint immediately
-
B
Facilitate a discussion between stakeholders and the Development Team to inspect the Increment and adapt the Product Backlog accordingly
-
C
Have the Development Team defend their completed work before accepting any changes
-
D
Postpone the Sprint Review until the Product Owner has a revised plan