A Product Owner notices that stakeholders keep requesting features that conflict with the current Sprint Goal. What is the BEST response?
-
A
Add the requests to the current Sprint immediately to keep stakeholders happy
-
B
Capture the requests in the Product Backlog and evaluate them against product goals at the next refinement
-
C
Reject all stakeholder requests that arrive mid-Sprint
-
D
Cancel the Sprint and restart planning to accommodate the new requests