A project team is using bottom-up estimating. What is the PRIMARY characteristic of this approach?
-
A
Estimates are based on similar past projects
-
B
Work packages are estimated individually and rolled up to total
-
C
A single expert provides the overall estimate
-
D
Statistical models calculate durations from variables