PMI-SP Time Estimating & Resource Allocation 4 — Questions and Answers
Question 1: A project team is using bottom-up estimating. What is the PRIMARY characteristic of this approach?
- Estimates are based on similar past projects
- Work packages are estimated individually and rolled up to total (Correct answer)
- A single expert provides the overall estimate
- Statistical models calculate durations from variables
Correct answer: Work packages are estimated individually and rolled up to total
Bottom-up estimating decomposes work into the smallest components, estimates each individually, and aggregates them for a total estimate.
Question 2: Resource allocation in a schedule is considered balanced when:
- All resources are assigned to critical path tasks only
- No resource is assigned more work than its available capacity (Correct answer)
- Each resource works the same number of hours per day
- Resources are shared equally across all project phases
Correct answer: No resource is assigned more work than its available capacity
Balanced resource allocation means no resource is over-allocated beyond its available capacity at any point in the schedule.
Question 3: What is the purpose of management reserve in the context of time estimating?
- To account for identified risks with quantified probability
- To provide buffer for unknown-unknown risks that may extend the schedule (Correct answer)
- To pad individual activity estimates for team convenience
- To store extra budget for approved scope changes
Correct answer: To provide buffer for unknown-unknown risks that may extend the schedule
Management reserve is set aside for unknown risks (unknown-unknowns) that cannot be planned for and may unexpectedly extend the schedule.
Question 4: When estimating activity durations, which factor is MOST important to capture in the activity attributes?
- The project sponsor's preferred timeline
- Assumptions and constraints influencing the estimate (Correct answer)
- The number of team members who reviewed the estimate
- The cost baseline for the activity
Correct answer: Assumptions and constraints influencing the estimate
Recording assumptions and constraints in activity attributes ensures the basis for the estimate is documented and traceable during schedule management.
Question 5: Which scheduling constraint is MOST likely to force resource leveling to push a task past its late finish date?
- Finish-to-start dependency
- Resource over-allocation (Correct answer)
- Mandatory start date
- External dependency
Correct answer: Resource over-allocation
Resource over-allocation is the primary driver for resource leveling, which may delay tasks beyond their late finish date, creating negative float.
Question 6: A schedule has contingency reserves applied to individual activities. These reserves are meant to handle:
- Scope creep approved by the change control board
- Known risks identified in the risk register (Correct answer)
- Unknown risks outside the project manager's control
- Team member turnover and replacement costs
Correct answer: Known risks identified in the risk register
Contingency reserves are allocated for identified known-unknown risks quantified during risk analysis and included in the schedule baseline.
Question 7: In a resource-constrained schedule, which activity should typically receive resource priority when two tasks compete for the same resource?
- The activity with the highest cost estimate
- The activity with the least total float (Correct answer)
- The activity assigned to the most senior resource
- The activity with the most predecessors
Correct answer: The activity with the least total float
Activities with the least total float are closest to becoming critical and should receive resource priority to avoid jeopardizing the project end date.
A project team is using bottom-up estimating.
What is the PRIMARY characteristic of this approach?