PMI-SP Cheat Sheet 2026
The 30 highest-yield PMI-SP facts, distilled from real exam questions. Print it, save it as a PDF, or study it here — free, no sign-up.
170 questions
210 min time limit
61% to pass
- When applying the critical chain method, buffers are placed at the end of the project to protect which schedule element? → The project completion date
- During a project status review, EV equals PV. What does this tell the project manager? → The project is on schedule
- A PMI-SP professional discovers a conflict of interest in a current assignment. What is the MOST ethical course of action? → Disclose the conflict immediately and recuse if necessary
- When estimating activity durations, which factor is MOST important to capture in the activity attributes? → Assumptions and constraints influencing the estimate
- Which duration estimating technique is MOST appropriate when a project team has little historical data but access to subject matter experts? → Expert judgment
- A project's Estimate to Complete (ETC) is calculated as EAC - AC. This formula is used when: → The original estimate is considered fundamentally flawed and a new estimate is prepared
- During schedule control, what is the MAIN purpose of trend analysis? → To forecast future schedule performance based on historical performance data
- Which of the following is an example of a leading indicator used in schedule monitoring? → Percentage of planned activities started on time in the current period
- Which estimating technique is MOST appropriate early in a project when detailed scope information is not yet available? → Analogous estimating
- A project's SPI is 0.85 at month 6. The project manager knows SPI tends to converge toward 1.0 near project end. What risk does this create for EVM forecasting? → SPI may mask persistent schedule problems as the denominator (PV) grows toward BAC
- Why is contingency planning important in project scheduling? → To create alternative plans that minimize delays and address unforeseen risks
- A PMI-SP certified professional is asked to provide services outside their scope of competence. The CORRECT ethical response is to: → Decline and refer to a qualified professional
- In a precedence diagramming method (PDM) network, a Start-to-Start relationship with a lag of 2 days means: → The successor can start 2 days after the predecessor starts
- Which component of the schedule management plan specifies the level of accuracy required for activity duration estimates? → Level of accuracy
- In the context of PMI-SP, what does 'risk appetite' mean for schedule management decisions? → The degree of uncertainty an organization is willing to accept regarding schedule outcomes
- Which type of schedule report provides the MOST comprehensive view by combining scope, schedule, and cost performance in one dashboard? → Earned Value Management dashboard
- Which of the following metrics best forecasts the total project cost at completion, assuming current CPI remains constant? → EAC = BAC / CPI
- Which output of the Develop Schedule process provides the start and finish dates for project activities? → Project schedule
- When resources are leveled on a schedule, which of the following is the most common result? → The project duration is extended
- What role does collaboration play in progress tracking for PMI-SP professionals? → It enhances outcomes through diverse perspectives and shared expertise
- A client requests that several low-priority activities be deferred to a later phase. How should the schedule baseline be adjusted? → Submit a formal change request; upon approval, update the baseline to reflect the deferral
- Which output of the Sequence Activities process is a graphical representation of all scheduled activities and their logical relationships? → Project schedule network diagram
- Which professional attribute is most valued in duration estimating within the PMI-SP field? → Accountability and commitment to standards
- What role does collaboration play in activity sequencing for PMI-SP professionals? → It enhances outcomes through diverse perspectives and shared expertise
- A risk breakdown structure (RBS) is MOST useful in schedule risk management for: → Organizing and categorizing risks to identify patterns and ensure coverage
- A PMI-SP is reviewing a schedule where the predecessor relationship between Design and Procurement is listed as 'FF+10d'. What does this mean? → Procurement cannot finish until 10 days after Design finishes
- What is the value of continuing education in duration estimating for PMI-SP professionals? → It keeps professionals current with evolving standards and practices
- Which float value measures the amount of time an activity can be delayed without delaying the project finish date? → Total float
- In EVM, which baseline serves as the time-phased budget against which project performance is measured? → Performance Measurement Baseline (PMB)
- In PMI-SP practice, what is the best approach to quality improvement in progress tracking? → Use data-driven methods with measurable outcomes