Resource leveling is primarily used to resolve which type of scheduling conflict?
Select your answer
A
Float consumption on critical activities
B
Over-allocation of resources beyond availability limits
C
Inaccurate duration estimates on summary tasks
D
Incorrect predecessor-successor relationships