(PMI-SP) PMI Scheduling Professional Practice Test
โ
๐ PMI-SP Practice Tests
Activity Sequencing
Baseline Management
Critical Path Method
Duration Estimating
Earned Value
Fundamentals & Core Concepts
Monitoring, Controlling & Reporting Schedules
Professional Ethics & Conduct
Progress Tracking
Resource Leveling & Optimization
Risk Analysis & Contingency Planning
Safety & Risk Management
Schedule Compression
Schedule Development & Management
Schedule Tools
๐ PMI-SP Study Guides
PMI-SP Exam #1
๐ฅ PMI-SP Videos
๐ PMI-SP VIP Scheduling Professional Certification Exam
Flashcards
PMI-SP Flashcards
๐ PMI-SP VIP Flashcards
Study Guide
PMI-SP Study Guide
Cheat Sheet
PMI-SP Cheat Sheet
Articles
PMI-SP Practice Test PDF (Free Printable 2026)
Unlocking Career Opportunities in Project Management: PMI Scheduling Professional
โฐ
(PMI-SP) PMI Scheduling Professional Practice Test
โถ
PMI-SP Time Estimating & Resource Allocation 3
Free ยท Instant Results
An activity has an optimistic estimate of 3 days, a pessimistic estimate of 15 days, and a most likely estimate of 6 days. What is the PERT expected duration?
A
6 days
B
7 days
C
8 days
D
9 days