Practice Test Geeks home

PMI-SP Time Estimating & Resource Allocation 3

An activity has an optimistic estimate of 3 days, a pessimistic estimate of 15 days, and a most likely estimate of 6 days.
What is the PERT expected duration?

Select your answer