A project scheduler is using Monte Carlo simulation on a construction project. After 10,000 iterations, the P80 completion date is 3 weeks later than the deterministic schedule. What does this indicate?
-
A
The project will definitely finish 3 weeks late
-
B
There is an 80% probability the project finishes on or before that date
-
C
The schedule baseline must be extended by 3 weeks immediately
-
D
Monte Carlo results are unreliable and should be discarded