Practice Test Geeks home

PMI-SP Risk Analysis & Contingency Planning 2

A project scheduler is using Monte Carlo simulation on a construction project.
After 10,000 iterations, the P80 completion date is 3 weeks later than the deterministic schedule.

What does this indicate?

Select your answer