A project manager assigns each identified risk a probability score of 1-5 and an impact score of 1-5, then multiplies them. What technique is being used?
-
A
Probability and impact matrix
-
B
Decision tree analysis
-
C
Monte Carlo simulation
-
D
Expected monetary value analysis