During risk monitoring, a previously identified risk has not occurred and its triggers are no longer relevant. What is the appropriate action?
-
A
Close the risk and update the risk register
-
B
Escalate the risk to the sponsor
-
C
Increase the contingency reserve
-
D
Re-perform quantitative analysis