How is risk appetite best defined in the PMI-RMP framework?
-
A
The amount of risk an organization is willing to pursue to achieve objectives
-
B
The total budget allocated for risk contingency
-
C
The number of risks identified in the risk register
-
D
The probability that all risks will occur