A project team proposes a high-risk strategy with potential 40% cost savings. The organization's risk appetite is low. What should the PMI-RMP practitioner recommend?
-
A
Proceed immediately to maximize savings
-
B
Evaluate whether the strategy aligns with organizational risk appetite before proceeding
-
C
Ignore the risk appetite and focus on cost savings
-
D
Transfer all risk to the vendor