A construction project faces a high probability of significant delays due to forecasted severe weather during a critical foundation-pouring phase. To counter this, the project manager revises the project schedule to complete the foundation work two months earlier, during a season with historically stable weather. This action is a clear example of which threat response strategy?
-
A
Mitigate
-
B
Transfer
-
C
Avoid
-
D
Accept