A project manager is facilitating a risk identification workshop. The team identifies a potential risk, its cause, and its potential impact on the project schedule. According to the PMBOK® Guide, what is the most appropriate next step for the project manager regarding this newly identified risk?
-
A
Develop a comprehensive risk response plan immediately.
-
B
Perform a quantitative analysis to determine the exact financial impact.
-
C
Add the risk, along with its characteristics, to the risk register.
-
D
Escalate the risk to the project sponsor for awareness and direction.