A project manager is developing the Risk Management Plan for a large, complex construction project. The organization has a standard risk management framework, but the project manager recognizes that it needs to be adapted for the specific needs of this project. Which of the following is the BEST example of tailoring the risk management framework?
-
A
Adhering strictly to every process and template in the corporate framework to ensure compliance.
-
B
Refining risk thresholds and creating a custom Risk Breakdown Structure (RBS) specific to construction risks.
-
C
Using only the risk register template from the organizational framework and ignoring other elements.
-
D
Assigning all risk management responsibilities to a single dedicated risk officer.