A project manager for a highly innovative and unprecedented technology project needs to identify potential risks. Since there is no historical data and the team members' opinions are strongly influenced by a few dominant personalities, the project manager wants to gather expert judgment anonymously to avoid bias. Which risk identification tool is MOST appropriate for this situation?
-
A
Brainstorming Session
-
B
Delphi Technique
-
C
SWOT Analysis
-
D
Checklist Analysis