A project manager is managing a large-scale construction project with significant uncertainty in the duration of several critical path activities. To understand the overall impact of this uncertainty on the project completion date and to determine the probability of finishing by the contractual deadline, which quantitative risk analysis technique would be MOST appropriate?
-
A
Decision Tree Analysis
-
B
Sensitivity Analysis
-
C
Monte Carlo Simulation
-
D
Expected Monetary Value (EMV) Analysis