A project team has identified 75 risks and is using a 5x5 probability and impact matrix to prioritize them. A specific risk is assessed as having a 'Very High' impact but a 'Very Low' probability. Where would this risk typically be placed for future monitoring?
-
A
Immediately escalated to the project sponsor
-
B
On a watchlist within the risk register
-
C
Sent for immediate quantitative analysis
-
D
In a dedicated contingency fund document