A project team discovers that a new software algorithm could significantly improve the final product's performance, a key project objective. To guarantee this benefit is realized, the project manager allocates top talent and additional funding to integrate the algorithm, making its successful implementation a primary focus. Which opportunity response strategy is the project manager using?
-
A
Enhance
-
B
Accept
-
C
Share
-
D
Exploit