A project is 60% complete. The project manager notes that the cost performance index (CPI) is 0.9 and several identified risks have occurred, consuming 75% of the contingency reserves. What is the MOST appropriate immediate action for the project manager to take during the Monitor Risks process?
-
A
Request additional funding from the sponsor immediately.
-
B
Analyze the remaining risks and the adequacy of the remaining reserves.
-
C
Crash the schedule to try to improve the CPI.
-
D
Update the risk management plan to reduce the number of identified risks.