A resistant stakeholder has significant political influence over the project's funding. Which engagement approach is MOST appropriate?
-
A
Avoid engaging them to prevent conflict
-
B
Engage them early and often with transparent, tailored information
-
C
Rely on the sponsor to manage them exclusively
-
D
Reduce their access to project information