A project manager discovers a previously unidentified stakeholder group midway through execution. What is the FIRST action to take?
-
A
Ignore them since the project is already underway
-
B
Add them to the stakeholder register and assess their influence and interest
-
C
Immediately escalate to the project sponsor
-
D
Revise the project charter to include the new group