A project team uses the 100% rule when building their WBS. This means:
-
A
Every team member must contribute at least one work package
-
B
The WBS captures 100% of the work defined in the scope and no more
-
C
All work packages must be exactly 100 hours in duration
-
D
The WBS must be approved by 100% of stakeholders