A project manager is creating a WBS and cannot determine how to decompose a future deliverable because requirements are unclear. What is the best approach?
-
A
Delete the deliverable from the WBS entirely
-
B
Use a planning package to represent that portion of scope
-
C
Estimate the deliverable at the highest level and proceed
-
D
Request the sponsor to reduce project scope