A project manager notices that a team member is bypassing the change control process to avoid delays. What is the MOST appropriate response?
-
A
Allow it since the team member has good intentions
-
B
Coach the team member on governance requirements and reinforce the change control process
-
C
Report the team member to senior management immediately without discussion
-
D
Retroactively approve all unauthorized changes to maintain project momentum