A Change Control Board (CCB) rejects a change request that the project manager believes is critical. What should the project manager do NEXT?
-
A
Implement the change anyway since it is critical to success
-
B
Accept the decision and document it in the change log
-
C
Bypass the CCB and get sponsor approval directly
-
D
Close the project because the rejection makes success impossible