A project sponsor requests early termination of a project because market conditions have changed and the original benefits are no longer achievable. This decision is best guided by:
-
A
The project quality plan
-
B
An updated business case showing the project no longer delivers sufficient value
-
C
The project manager's authority to continue
-
D
Stakeholder satisfaction scores