A project manager notices that mid-project scope changes are eroding the original business case. Which action best preserves benefits realization?
-
A
Reject all scope changes to protect the baseline
-
B
Re-evaluate the business case and update the benefits register
-
C
Escalate to the sponsor and halt the project
-
D
Continue delivery and address benefits after go-live